Attleboro High School Project Weekly Update

Weekly update from Consigli Construction:

Week of 10/14/2019:

  • Excavate for new building footings
  • Remove topsoil from site
  • Pave laydown area near trailers (10/17 – pending weather)
  • Install gas meter at the sewer pump station (Awaiting Columbia Gas)
  • Truck excess soil and debris off site
  • Pipe water and sewer to the trailers
  • Import structural fill at foundations
  • Transfer services to the new utility poles (National Grid and others)
  • Layout and form footings in Bldg C