Below are the projected work activities for this week provided by Consigli.
Neighborhood Impact
- Steel deliveries
- Trucking of loam off site
- Concrete trucks
- Construction lights on 4th floor of building
- Work at Highland Park
Week of 5/11/2020:
- Steel deliveries and erection
- Slab on deck concrete pour – Area C 4th floor and Area A roof (5/14 – 6:30am start)
- Underground plumbing in Area F
- Trucking loam off site
- Install CMU shaft at Stair C11 & F12
- Install roof blocking in Area C
- Underground utilities within site fence
- Roofing deliveries
- Punch list items at Highland Park (weather dependent)