Attleboro High School Project Weekly Update

Weekly update from Consigli Construction:


Week of 8/19/19 


  • Grade (8/19 & 8/20) west end of Rathbun Willard Dr, Drummond St, Rome Blvd and rotary (New traffic pattern)
  • Pave (8/21) west end of Rathbun Willard Dr, Drummond St, Rome Blvd and rotary (New traffic pattern)
  • Grade (8/22) east end of Rathbun Willard Dr.
  • Pave (8/23) east end of Rathbun Willard Dr.
  • Install water line (8/20) at new Rathbun Willard Dr. (Brennan School – no water 7am-3pm)
  • Install water line (8/21) at Green Dr (Green Dr and Fairway Dr – no water 7am-3pm)
  • Complete drainage line and manholes along Rathbun Willard Dr.
  • Complete gas piping along Rathbun Willard Dr
  • Demo existing breaching in boiler room (one boiler to remain active at all times)
  • Prep for cooling tower relocation






Facebook Twitter Email

Other News in Home

Mechanic Street Sidewalks

Posted on: June 26, 2019

Resurfacing Notice FY2020

Posted on: June 4, 2019

2019 Yearly Operational Plan

Posted on: May 20, 2019

HIGHLAND PARK FUTURE USE REPORT

Posted on: February 20, 2019

Tax Exemption Information

Posted on: May 29, 2018

Debt Exclusion Calculation

Posted on: April 18, 2018