News Flash

Home

Posted on: July 16, 2019

Attleboro High School Project Weekly Update

Below are the projected work activities for this week, provided by Consigli.

Neighborhood Impact 

  • Concrete trucks
  • Utility pole removal
  • Generators for temp heaters
  • Steel deliveries

 

 

Week of 1/20/2020:

 

  • Excavate for new building footings
  • Remove existing utility poles (Comcast/Verizon)
  • Layout/form/rebar/pour footings and walls in Area D, G, J and K
  • National Grid working on high voltage cut over
  • Steel deliveries and erection
  • Remove and backfill old stack footing (1/20)

Facebook Twitter Email

Other News in Home

Winter Parking Ban

Posted on: November 5, 2019

2019 Yearly Operational Plan

Posted on: May 20, 2019

HIGHLAND PARK FUTURE USE REPORT

Posted on: February 20, 2019

Tax Exemption Information

Posted on: May 29, 2018

Debt Exclusion Calculation

Posted on: April 18, 2018