Attleboro High School Project Weekly Update

Below are the projected work activities for this week provided by Consigli.


Neighborhood Impact 

  • Steel deliveries
  • Trucking of loam off site
  • Concrete trucks
  • Construction lights on 4th floor of building
  • Work at Highland Park

 

 

Week of 5/11/2020:

 

  • Steel deliveries and erection
  • Slab on deck concrete pour – Area C 4th floor and Area A roof (5/14 – 6:30am start)
  • Underground plumbing in Area F
  • Trucking loam off site
  • Install CMU shaft at Stair C11 & F12
  • Install roof blocking in Area C
  • Underground utilities within site fence
  • Roofing deliveries
  • Punch list items at Highland Park (weather dependent)

Facebook Twitter Email

Other News in Home

Fall Curbside Yard Waste Collection

Posted on: September 21, 2020

Covid-19 We are all in this together

Posted on: September 17, 2020

Mandatory Water Ban

Posted on: September 15, 2020

Services at Government Center

Posted on: May 26, 2020

Trash Carts

Posted on: August 27, 2020
IMG_3670

Ballot Drop Box

Posted on: August 20, 2020

Compost Center

Posted on: July 28, 2020

Rubbish Program Update

Posted on: July 13, 2020

New Launch of downtownattleboro.com

Posted on: June 16, 2020

City Wide Paving Projects

Posted on: March 27, 2020

HIGHLAND PARK FUTURE USE REPORT

Posted on: February 20, 2019

Tax Exemption Information

Posted on: May 29, 2018

Debt Exclusion Calculation

Posted on: April 18, 2018